Heritage Park is going to receive some updates and this page is your source for the latest news, construction progress, and important information related to the renovation of Corcoran's most-used park!
About the Project
The project is an investment in the future of Corcoran's park system. This project includes upgrades to key amenities, infrastructure, and accessibility. Planned improvements include:
NEW Farm-Themed Playground
NEW Park Building
NEW and Improved Trail Connections
NEW Paved Parking Lot
NEW Ballfield Irrigation
Improved Field Conditions
These changes are designed to better serve residents of all ages and abilities, and to create a more welcoming, inclusive public space for generations to come!
Construction & Park Access
Construction is scheduled to begin the week of July 14, 2025.
Starting Monday, July 14, the western portion of the park will be closed.
By Wednesday, July 16, the remainder of the park will be closed, except Snyder and Meister Fields. Please note: While these two fields may remain in use, access may be limited or unavailable at times due to construction activity. Users should plan ahead and watch for signage.
Substantial completion anticipated for October 2025.
Final completion is anticipated for May 2026.
Follow Along with the Progress
This page will be updated regularly with construction status updates, timeline adjustments, photos of progress, notices of access, and frequently asked questions. We encourage you to check back often as we move through each phase of the project. Thank you for your patience and support as we work to improve one of Corcoran's most beloved community spaces!
August – September 2025
September – November 2025
- Earthwork (CMU, slab pouring, footings)
- Seeding (late September)
- Landscaping and irrigation (late September – mid-October)
October 2025
- Curbing (early October)
- Concrete flatwork/sidewalks (early October)
- Parking lot and trail paving (mid-October)
- Lighting installation (mid-October)
- Final seeding (mid-October)
November 2025 – February 2026
- Exterior construction (trash enclosure, building erection, roofing, framing)
January – March 2026
- Interior construction (insulation, drywall, counters, finishing, electrical/HVAC trim-out)
Winter 2025 – Spring 2026
Spring 2026
- Paving parking lot wear course
- Parking lot striping